Skip to content
Sample comparison

Inspect a finding. Follow it to the bid.

One plumbing — div 22 package, 40 scope lines, and 3 subcontractor bids. Choose a status below to inspect the recorded assessment and supporting evidence.

Synthetic scope and bids. Recorded Prestead analysis. This demonstrates the workflow, not measured accuracy.

Recorded analysis: September 6, 2026 · View provenance

Recorded at 2026-09-06T06:52:19.095Z. The analysis has not been rerun or edited for this presentation. Pipeline versions recorded with that run:

  • template-parsing: 2026-09-05.1
  • scope-extraction: 2026-07-12.1
  • bid-parsing: 2026-09-05.1
  • gap-analysis: 2026-09-05.1
  • clarification-drafting: 2026-09-05.1

In the print dialog, choose Save as PDF.

Four scope examples, in template order

Plumbing comparisonSynthetic sample
Capital Mechanical Inc.AI excluded · Not reviewed

Performance and payment bonds, 100%, included in base bid.

Scope: p. 1, item 2

Performance and Payment Bonds — add 2.0% if required by the GC.
Bid_C_Capital_Mechanical.pdf · p. 2

AI confidence: high · Certainty in this assessment

Conditional — bonds available for add of 2.0%; scope sheet requires them in base bid.

Select a status to inspect the recorded evidence. Read-only.

Prestead fills your scope template from the uploaded bid PDFs only. The spec and drawings are not reviewed.

This walkthrough is read-only. Selecting a finding does not mark it reviewed. Silent means “Not addressed in bid” and has no invented quotation.

Open the synthetic source PDFs

The complete comparison report

Scroll within the report to inspect every scope line and the full evidence appendix. This is an unreviewed first pass: no human overrides or invented carries. Incomplete pricing remains qualified and unranked.

Sample projectPlumbing — Div 22

3 of 3 submissions analyzed.

Synthetic scope and bids. Recorded Prestead analysis. This demonstrates the workflow, not measured accuracy. Analysis recorded 2026-09-06T06:52:19.095Z.

Prestead fills your scope template from the uploaded bid PDFs only. The spec and drawings are not reviewed.

Comparison

ScopeLocatorReliable Mechanical Co.Cost adjustment (CAD)Northern Plumbing Ltd.Cost adjustment (CAD)Capital Mechanical Inc.Cost adjustment (CAD)
Analyzed submissions: 3 of 3
General
Permits, inspection fees and tap fees for all plumbing work.page 1, item 1Excluded · Not reviewedExcluded · Not reviewedExcluded · Not reviewed
Performance and payment bonds, 100%, included in base bid.page 1, item 2Excluded · Not reviewedExcluded · Not reviewedExcluded · Not reviewed
Prevailing wage / federal Fair Wage Schedule rates per Schedule D.page 1, item 3Silent · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Bid security or bid bond with tender submission.page 1, item 4Included · Not reviewedSilent · Not reviewedSilent · Not reviewed
Attend weekly coordination meetings with GC and other trades.page 1, item 5Silent · Not reviewedSilent · Not reviewedUnclear · Not reviewed
Temporary heat for our own work; permanent systems not to be used for construction heat.page 1, item 6Silent · Not reviewedSilent · Not reviewedSilent · Not reviewed
Housekeeping pads for all floor-mounted plumbing equipment.page 1, item 7Excluded · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Coordination drawings (BIM LOD 300) for underground and overhead piping.page 1, item 8Silent · Not reviewedSilent · Not reviewedSilent · Not reviewed
Cutting, patching and core drilling, including patching of finished surfaces.page 1, item 9Included · Not reviewedExcluded · Not reviewedIncluded · Not reviewed
Fire-rated sealing of all plumbing penetrations through rated assemblies, ULC-listed fill.page 1, item 10Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Domestic Water & Drainage
Domestic cold, hot and recirculation piping complete with valves and insulation.page 1, item 11Included · Not reviewedIncluded · Not reviewedIncluded · Not reviewed
Sanitary, vent and storm drainage piping complete.page 1, item 12Included · Not reviewedIncluded · Not reviewedIncluded · Not reviewed
Lab waste and acid-resistant drainage piping including neutralization basin.page 1, item 13Included · Not reviewedIncluded · Not reviewedIncluded · Not reviewed
RO water and softened water distribution piping.page 1, item 14Included · Not reviewedIncluded · Not reviewedIncluded · Not reviewed
Plumbing fixtures and trim per schedule, including carriers and final connections.page 1, item 15Unclear · Not reviewedIncluded · Not reviewedUnclear · Not reviewed
Furnish and install domestic water heater, expansion tank and recirculation pump.page 1, item 16Unclear · Not reviewedExcluded · Not reviewedUnclear · Not reviewed
Disinfection of new and existing potable piping; bacteriological samples from certified lab.page 1, item 17Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Pressure test all domestic water AND drainage systems; submit test certificates.page 1, item 18Silent · Not reviewedIncluded · Not reviewedIncluded · Not reviewed
Compressed Air & Specialty Piping
Compressed air piping, Schedule 80 seamless black steel, ASME B16.11 socket-welded fittings.page 1, item 19Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Three-piece ball valves ASTM A181 Class 70 on compressed air, with couplers and shut-offs.page 1, item 20Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Pressure test compressed air system at 1100 kPa for 4 hours.page 1, item 21Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Bronze valves, CRN-registered, single manufacturer: gate, globe, check, ball and butterfly.page 1, item 22Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Pipe welding by CSA B51 qualified welders to ASME B31.1, procedures registered.page 1, item 23Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Third-party weld inspection and radiography of welded joints.page 1, item 24Unclear · Not reviewedSilent · Not reviewedSilent · Not reviewed
Fire Protection
Wet pipe sprinkler system designed and installed to NFPA 13, hydraulically calculated.page 1, item 25Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Manitoba-stamped PE shop drawings for sprinkler layout.page 1, item 26Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Spare sprinkler heads and wrench cabinet per NFPA 13 minimum.page 1, item 27Silent · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Integrated systems testing of fire protection per CAN/ULC-S1001.page 1, item 28Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Site painting of sprinkler piping: primer, finish coats, 50mm red enamel bands at 6m o.c.page 1, item 29Included · Not reviewedExcluded · Not reviewedExcluded · Not reviewed
Hangers, Supports & Identification
Pipe hangers and supports per MSS SP-58 with spacing per the spec table.page 1, item 30Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
PE-stamped shop drawings for anchors, guides and seismic restraints.page 1, item 31Included · Not reviewedUnclear · Not reviewedIncluded · Not reviewed
Galvanized hangers at exterior and unheated locations; insulation protection shields.page 1, item 32Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Structural steel supports for equipment referenced to Section 05 12 23.page 1, item 33Excluded · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Mechanical identification per CAN/CGSB-24.3: pipe legends, flow arrows, valve tags.page 1, item 34Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Thermometers and pressure gauges at equipment connections.page 1, item 35Excluded · Not reviewedSilent · Not reviewedExcluded · Not reviewed
Closeout
O&M manuals: equipment data, valve schedules, test certificates, subcontractor manuals.page 1, item 36Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
As-built drawings: reviewed shop drawings and marked-up construction set.page 1, item 37Included · Not reviewedSilent · Not reviewedIncluded · Not reviewed
Owner training: five (5) Working Days of instruction for the Owner's representative.page 2, item 38Included · Not reviewedSilent · Not reviewedExcluded · Not reviewed
One-year warranty on all labour and materials from Substantial Performance.page 2, item 39Silent · Not reviewedUnclear · Not reviewedIncluded · Not reviewed
Final cleaning and removal of all debris from work areas.page 2, item 40Silent · Not reviewedSilent · Not reviewedSilent · Not reviewed
Submitted base487,500398,200432,800
CurrencyCADCADCAD
Scope cost adjustments000
Bid adjustments000
Adjusted total487,500398,200432,800
Completeness16 gaps unpriced34 gaps unpriced23 gaps unpriced
SubmissionRevision 1: Bid_A_Reliable_Mechanical.pdfRevision 1: Bid_B_Northern_Plumbing.pdfRevision 1: Bid_C_Capital_Mechanical.pdf

Evidence appendix

Reliable Mechanical Co. · Revision 1 · Permits, inspection fees and tap fees for all plumbing work.

General · page 1, item 1 · Excluded · Not reviewed

Permit fees and inspection fees by General Contractor.

Bid_A_Reliable_Mechanical.pdf, p. 2

Scope sheet assigns permits, inspection and tap fees to this package; bid pushes to GC. Tap fees not named.

Northern Plumbing Ltd. · Revision 1 · Permits, inspection fees and tap fees for all plumbing work.

General · page 1, item 1 · Excluded · Not reviewed

Permits and inspection fees.

Bid_B_Northern_Plumbing.pdf, p. 1

Bid excludes permits and inspection fees; tap fees not mentioned at all.

Capital Mechanical Inc. · Revision 1 · Permits, inspection fees and tap fees for all plumbing work.

General · page 1, item 1 · Excluded · Not reviewed

Permits, inspection fees, and tap fees by GC or Owner.

Bid_C_Capital_Mechanical.pdf, p. 2

Scope sheet assigns permits/fees to this package; bid pushes to GC/Owner.

Reliable Mechanical Co. · Revision 1 · Performance and payment bonds, 100%, included in base bid.

General · page 1, item 2 · Excluded · Not reviewed

Performance and Payment Bonds excluded — add 1.75% if required.

Bid_A_Reliable_Mechanical.pdf, p. 2

Conditional — add alternate of $8,500 / 1.75% if bonds required; scope sheet requires them in base bid.

Northern Plumbing Ltd. · Revision 1 · Performance and payment bonds, 100%, included in base bid.

General · page 1, item 2 · Excluded · Not reviewed

Performance and Payment bonds.

Bid_B_Northern_Plumbing.pdf, p. 1

Scope sheet requires 100% bonds in base bid; bid excludes them — price adjustment needed.

Capital Mechanical Inc. · Revision 1 · Performance and payment bonds, 100%, included in base bid.

General · page 1, item 2 · Excluded · Not reviewed

Performance and Payment Bonds — add 2.0% if required by the GC.

Bid_C_Capital_Mechanical.pdf, p. 2

Conditional — bonds available for add of 2.0%; scope sheet requires them in base bid.

Reliable Mechanical Co. · Revision 1 · Prevailing wage / federal Fair Wage Schedule rates per Schedule D.

General · page 1, item 3 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid does not address prevailing wage or Fair Wage Schedule D; commercial term, confirm inclusion.

Northern Plumbing Ltd. · Revision 1 · Prevailing wage / federal Fair Wage Schedule rates per Schedule D.

General · page 1, item 3 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid does not address prevailing wage or Fair Wage Schedule D.

Capital Mechanical Inc. · Revision 1 · Prevailing wage / federal Fair Wage Schedule rates per Schedule D.

General · page 1, item 3 · Excluded · Not reviewed

Prevailing wage / Fair Wage Schedule premium: Our pricing is based on standard Manitoba commercial rates. If this project triggers federal Fair Wage Schedule rates (per the spec's Schedule D reference), add 6% to the base bid.

Bid_C_Capital_Mechanical.pdf, p. 2

Base bid excludes Fair Wage premium; add 6% to comply with Schedule D.

Reliable Mechanical Co. · Revision 1 · Bid security or bid bond with tender submission.

General · page 1, item 4 · Included · Not reviewed

Bid Bond included with this submission.

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Bid security or bid bond with tender submission.

General · page 1, item 4 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid excludes performance/payment bonds but is silent on bid security — confirm.

Capital Mechanical Inc. · Revision 1 · Bid security or bid bond with tender submission.

General · page 1, item 4 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid addresses performance/payment bonds only; bid security not mentioned.

Reliable Mechanical Co. · Revision 1 · Attend weekly coordination meetings with GC and other trades.

General · page 1, item 5 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid mentions only a pre-installation meeting per Section 22 15 00; weekly coordination meetings not addressed.

Northern Plumbing Ltd. · Revision 1 · Attend weekly coordination meetings with GC and other trades.

General · page 1, item 5 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Attend weekly coordination meetings with GC and other trades.

General · page 1, item 5 · Unclear · Not reviewed

Coordination with General Contractor and other trades.

Bid_C_Capital_Mechanical.pdf, p. 1

General coordination statement does not confirm attendance at weekly coordination meetings.

Reliable Mechanical Co. · Revision 1 · Temporary heat for our own work; permanent systems not to be used for construction heat.

General · page 1, item 6 · Silent · Not reviewed

Not addressed in bid

Page not available

No mention of temporary heat or use of permanent systems for construction heat.

Northern Plumbing Ltd. · Revision 1 · Temporary heat for our own work; permanent systems not to be used for construction heat.

General · page 1, item 6 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Temporary heat for our own work; permanent systems not to be used for construction heat.

General · page 1, item 6 · Silent · Not reviewed

Not addressed in bid

Page not available

No mention of temporary heat in inclusions or exclusions.

Reliable Mechanical Co. · Revision 1 · Housekeeping pads for all floor-mounted plumbing equipment.

General · page 1, item 7 · Excluded · Not reviewed

Excludes housekeeping concrete pads (Section 23 05 29 references Section 03 30 00).

Bid_A_Reliable_Mechanical.pdf, p. 2

Scope sheet assigns housekeeping pads to this package; confirm who carries them.

Northern Plumbing Ltd. · Revision 1 · Housekeeping pads for all floor-mounted plumbing equipment.

General · page 1, item 7 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Housekeeping pads for all floor-mounted plumbing equipment.

General · page 1, item 7 · Excluded · Not reviewed

Excludes housekeeping pads (Section 03 30 00) and structural supports referenced to Section 05 12 23.

Bid_C_Capital_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Coordination drawings (BIM LOD 300) for underground and overhead piping.

General · page 1, item 8 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid references coordination with Division 26 but never BIM LOD 300 coordination drawings.

Northern Plumbing Ltd. · Revision 1 · Coordination drawings (BIM LOD 300) for underground and overhead piping.

General · page 1, item 8 · Silent · Not reviewed

Not addressed in bid

Page not available

No mention of BIM/coordination drawings; potential unbudgeted cost.

Capital Mechanical Inc. · Revision 1 · Coordination drawings (BIM LOD 300) for underground and overhead piping.

General · page 1, item 8 · Silent · Not reviewed

Not addressed in bid

Page not available

No mention of BIM LOD 300 coordination drawings; general coordination language does not affirm it.

Reliable Mechanical Co. · Revision 1 · Cutting, patching and core drilling, including patching of finished surfaces.

General · page 1, item 9 · Included · Not reviewed

All cutting, patching, and core drilling required for plumbing work. Fire-rated sealing of penetrations through fire separation walls and floors with ULC-listed fill materials.

Bid_A_Reliable_Mechanical.pdf, p. 2

Bid covers cutting/patching generally; patching of finished surfaces not specifically affirmed.

Northern Plumbing Ltd. · Revision 1 · Cutting, patching and core drilling, including patching of finished surfaces.

General · page 1, item 9 · Excluded · Not reviewed

Cutting and patching of finished surfaces.

Bid_B_Northern_Plumbing.pdf, p. 1

Core drilling not addressed; patching of finished surfaces explicitly excluded.

Capital Mechanical Inc. · Revision 1 · Cutting, patching and core drilling, including patching of finished surfaces.

General · page 1, item 9 · Included · Not reviewed

Cutting and core drilling for plumbing work; fire-rated sealing of plumbing penetrations through rated assemblies with ULC-listed materials.

Bid_C_Capital_Mechanical.pdf, p. 1

Bid names cutting and core drilling; patching of finished surfaces not affirmed.

Reliable Mechanical Co. · Revision 1 · Fire-rated sealing of all plumbing penetrations through rated assemblies, ULC-listed fill.

General · page 1, item 10 · Included · Not reviewed

All cutting, patching, and core drilling required for plumbing work. Fire-rated sealing of penetrations through fire separation walls and floors with ULC-listed fill materials.

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Fire-rated sealing of all plumbing penetrations through rated assemblies, ULC-listed fill.

General · page 1, item 10 · Silent · Not reviewed

Not addressed in bid

Page not available

No firestopping language in inclusions or exclusions.

Capital Mechanical Inc. · Revision 1 · Fire-rated sealing of all plumbing penetrations through rated assemblies, ULC-listed fill.

General · page 1, item 10 · Included · Not reviewed

Cutting and core drilling for plumbing work; fire-rated sealing of plumbing penetrations through rated assemblies with ULC-listed materials.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · Domestic cold, hot and recirculation piping complete with valves and insulation.

Domestic Water & Drainage · page 1, item 11 · Included · Not reviewed

All Division 22 plumbing work as shown on drawings M-1.0 through M-8.4, including domestic water, sanitary, vent, storm, lab waste, RO water, and softened water systems.

Bid_A_Reliable_Mechanical.pdf, p. 1

Bid names domestic water generally; recirculation piping, valves and insulation not specifically affirmed.

Northern Plumbing Ltd. · Revision 1 · Domestic cold, hot and recirculation piping complete with valves and insulation.

Domestic Water & Drainage · page 1, item 11 · Included · Not reviewed

Domestic cold water, hot water, and recirculation piping including copper tube, fittings, valves, and connections.

Bid_B_Northern_Plumbing.pdf, p. 1

Insulation also covered separately by "Insulation of domestic hot and cold water piping."

Capital Mechanical Inc. · Revision 1 · Domestic cold, hot and recirculation piping complete with valves and insulation.

Domestic Water & Drainage · page 1, item 11 · Included · Not reviewed

Domestic water (hot, cold, recirculation), sanitary drainage, vent, storm drainage, lab waste, RO water, and softened water distribution systems.

Bid_C_Capital_Mechanical.pdf, p. 1

Piping systems named; valves and insulation not explicitly affirmed.

Reliable Mechanical Co. · Revision 1 · Sanitary, vent and storm drainage piping complete.

Domestic Water & Drainage · page 1, item 12 · Included · Not reviewed

All Division 22 plumbing work as shown on drawings M-1.0 through M-8.4, including domestic water, sanitary, vent, storm, lab waste, RO water, and softened water systems.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Sanitary, vent and storm drainage piping complete.

Domestic Water & Drainage · page 1, item 12 · Included · Not reviewed

Sanitary, vent, and storm drainage piping including cast iron and PVC where applicable.

Bid_B_Northern_Plumbing.pdf, p. 1

Capital Mechanical Inc. · Revision 1 · Sanitary, vent and storm drainage piping complete.

Domestic Water & Drainage · page 1, item 12 · Included · Not reviewed

Domestic water (hot, cold, recirculation), sanitary drainage, vent, storm drainage, lab waste, RO water, and softened water distribution systems.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · Lab waste and acid-resistant drainage piping including neutralization basin.

Domestic Water & Drainage · page 1, item 13 · Included · Not reviewed

All Division 22 plumbing work as shown on drawings M-1.0 through M-8.4, including domestic water, sanitary, vent, storm, lab waste, RO water, and softened water systems.

Bid_A_Reliable_Mechanical.pdf, p. 1

Lab waste named; acid-resistant piping and neutralization basin not specifically affirmed.

Northern Plumbing Ltd. · Revision 1 · Lab waste and acid-resistant drainage piping including neutralization basin.

Domestic Water & Drainage · page 1, item 13 · Included · Not reviewed

Lab waste and acid-resistant drainage piping.

Bid_B_Northern_Plumbing.pdf, p. 1

Piping covered; neutralization basin not named — confirm it is carried.

Capital Mechanical Inc. · Revision 1 · Lab waste and acid-resistant drainage piping including neutralization basin.

Domestic Water & Drainage · page 1, item 13 · Included · Not reviewed

Domestic water (hot, cold, recirculation), sanitary drainage, vent, storm drainage, lab waste, RO water, and softened water distribution systems.

Bid_C_Capital_Mechanical.pdf, p. 1

Lab waste piping named; acid-resistant material and neutralization basin not affirmed.

Reliable Mechanical Co. · Revision 1 · RO water and softened water distribution piping.

Domestic Water & Drainage · page 1, item 14 · Included · Not reviewed

All Division 22 plumbing work as shown on drawings M-1.0 through M-8.4, including domestic water, sanitary, vent, storm, lab waste, RO water, and softened water systems.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · RO water and softened water distribution piping.

Domestic Water & Drainage · page 1, item 14 · Included · Not reviewed

RO water and softened water distribution piping.

Bid_B_Northern_Plumbing.pdf, p. 1

Capital Mechanical Inc. · Revision 1 · RO water and softened water distribution piping.

Domestic Water & Drainage · page 1, item 14 · Included · Not reviewed

Domestic water (hot, cold, recirculation), sanitary drainage, vent, storm drainage, lab waste, RO water, and softened water distribution systems.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · Plumbing fixtures and trim per schedule, including carriers and final connections.

Domestic Water & Drainage · page 1, item 15 · Unclear · Not reviewed

All Division 22 plumbing work as shown on drawings M-1.0 through M-8.4, including domestic water, sanitary, vent, storm, lab waste, RO water, and softened water systems.

Bid_A_Reliable_Mechanical.pdf, p. 1

Blanket Division 22 claim lists systems only; fixtures, carriers and final connections not named.

Northern Plumbing Ltd. · Revision 1 · Plumbing fixtures and trim per schedule, including carriers and final connections.

Domestic Water & Drainage · page 1, item 15 · Included · Not reviewed

Plumbing fixtures and trim as scheduled on drawings, including connections.

Bid_B_Northern_Plumbing.pdf, p. 1

Carriers not specifically named; confirm fixture carriers are included.

Capital Mechanical Inc. · Revision 1 · Plumbing fixtures and trim per schedule, including carriers and final connections.

Domestic Water & Drainage · page 1, item 15 · Unclear · Not reviewed

All Division 22 plumbing as shown on Mechanical drawings M-1.0 through M-8.4 dated 2025-06-13 IFC, modified by addenda 1 through 3.

Bid_C_Capital_Mechanical.pdf, p. 1

Blanket Division 22 claim does not confirm fixtures, carriers and final connections are carried.

Reliable Mechanical Co. · Revision 1 · Furnish and install domestic water heater, expansion tank and recirculation pump.

Domestic Water & Drainage · page 1, item 16 · Unclear · Not reviewed

All Division 22 plumbing work as shown on drawings M-1.0 through M-8.4, including domestic water, sanitary, vent, storm, lab waste, RO water, and softened water systems.

Bid_A_Reliable_Mechanical.pdf, p. 1

Systems listed but equipment—water heater, expansion tank, recirculation pump—never named.

Northern Plumbing Ltd. · Revision 1 · Furnish and install domestic water heater, expansion tank and recirculation pump.

Domestic Water & Drainage · page 1, item 16 · Excluded · Not reviewed

Domestic water heater connections and piping (heater by others).

Bid_B_Northern_Plumbing.pdf, p. 1

Heater by others conflicts with scope sheet; expansion tank and recirc pump not addressed.

Capital Mechanical Inc. · Revision 1 · Furnish and install domestic water heater, expansion tank and recirculation pump.

Domestic Water & Drainage · page 1, item 16 · Unclear · Not reviewed

All Division 22 plumbing as shown on Mechanical drawings M-1.0 through M-8.4 dated 2025-06-13 IFC, modified by addenda 1 through 3.

Bid_C_Capital_Mechanical.pdf, p. 1

Blanket claim does not confirm water heater, expansion tank and recirculation pump are furnished.

Reliable Mechanical Co. · Revision 1 · Disinfection of new and existing potable piping; bacteriological samples from certified lab.

Domestic Water & Drainage · page 1, item 17 · Included · Not reviewed

Disinfection of all new and existing potable piping with minimum 50 ppm chlorine for 24 hours, flushing to under 0.2 ppm residual, and bacteriological samples from a certified laboratory.

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Disinfection of new and existing potable piping; bacteriological samples from certified lab.

Domestic Water & Drainage · page 1, item 17 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid covers pressure testing but never mentions disinfection or bacteriological sampling.

Capital Mechanical Inc. · Revision 1 · Disinfection of new and existing potable piping; bacteriological samples from certified lab.

Domestic Water & Drainage · page 1, item 17 · Included · Not reviewed

Disinfection of new and modified potable piping with 50 ppm chlorine for 24 hours, flushing to <0.2 ppm residual, and submission of bacteriological samples from a certified laboratory.

Bid_C_Capital_Mechanical.pdf, p. 1

Bid says 'new and modified'; scope line says new and existing — confirm coverage of existing piping.

Reliable Mechanical Co. · Revision 1 · Pressure test all domestic water AND drainage systems; submit test certificates.

Domestic Water & Drainage · page 1, item 18 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid lists testing for sprinkler and compressed air only; domestic water and drainage pressure testing not affirmed.

Northern Plumbing Ltd. · Revision 1 · Pressure test all domestic water AND drainage systems; submit test certificates.

Domestic Water & Drainage · page 1, item 18 · Included · Not reviewed

Pressure testing of all domestic water lines.

Bid_B_Northern_Plumbing.pdf, p. 1

Only domestic water testing affirmed; drainage testing and test certificates not covered.

Capital Mechanical Inc. · Revision 1 · Pressure test all domestic water AND drainage systems; submit test certificates.

Domestic Water & Drainage · page 1, item 18 · Included · Not reviewed

Standard pressure testing on domestic water and sanitary systems.

Bid_C_Capital_Mechanical.pdf, p. 1

Storm/vent drainage testing and test certificate submission not explicitly named, though O&M inclusion covers test certificates.

Reliable Mechanical Co. · Revision 1 · Compressed air piping, Schedule 80 seamless black steel, ASME B16.11 socket-welded fittings.

Compressed Air & Specialty Piping · page 1, item 19 · Included · Not reviewed

Section 22 15 00 — General Service Compressed Air Systems: Schedule 80 seamless black steel piping per ASTM A53/A53M, ASME B16.11 socket-welded fittings, three-piece ball valves to ASTM A181 Class 70, complete with all couplers, connectors, and shut-off valves as specified.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Compressed air piping, Schedule 80 seamless black steel, ASME B16.11 socket-welded fittings.

Compressed Air & Specialty Piping · page 1, item 19 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid offers steel pipe with threaded fittings; Sch 80 seamless with socket-welded ASME B16.11 fittings not affirmed.

Capital Mechanical Inc. · Revision 1 · Compressed air piping, Schedule 80 seamless black steel, ASME B16.11 socket-welded fittings.

Compressed Air & Specialty Piping · page 1, item 19 · Excluded · Not reviewed

Section 22 15 00 — Compressed Air Systems: EXCLUDED. The Schedule 80 welded compressed air system as specified is outside our standard scope; we recommend this be carried by a specialty piping contractor or added as Alternate #2 below.

Bid_C_Capital_Mechanical.pdf, p. 2

Available as Alternate #2 for $34,200 add.

Reliable Mechanical Co. · Revision 1 · Three-piece ball valves ASTM A181 Class 70 on compressed air, with couplers and shut-offs.

Compressed Air & Specialty Piping · page 1, item 20 · Included · Not reviewed

Section 22 15 00 — General Service Compressed Air Systems: Schedule 80 seamless black steel piping per ASTM A53/A53M, ASME B16.11 socket-welded fittings, three-piece ball valves to ASTM A181 Class 70, complete with all couplers, connectors, and shut-off valves as specified.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Three-piece ball valves ASTM A181 Class 70 on compressed air, with couplers and shut-offs.

Compressed Air & Specialty Piping · page 1, item 20 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid names bronze valves per drawings; three-piece ASTM A181 Class 70 valves not affirmed.

Capital Mechanical Inc. · Revision 1 · Three-piece ball valves ASTM A181 Class 70 on compressed air, with couplers and shut-offs.

Compressed Air & Specialty Piping · page 1, item 20 · Excluded · Not reviewed

Section 22 15 00 — Compressed Air Systems: EXCLUDED. The Schedule 80 welded compressed air system as specified is outside our standard scope; we recommend this be carried by a specialty piping contractor or added as Alternate #2 below.

Bid_C_Capital_Mechanical.pdf, p. 2

Compressed air valves fall within the excluded 22 15 00 scope; confirm under Alternate #2.

Reliable Mechanical Co. · Revision 1 · Pressure test compressed air system at 1100 kPa for 4 hours.

Compressed Air & Specialty Piping · page 1, item 21 · Included · Not reviewed

Pressure testing of compressed air systems at 1100 kPa for 4 hours per Section 22 15 00.

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Pressure test compressed air system at 1100 kPa for 4 hours.

Compressed Air & Specialty Piping · page 1, item 21 · Silent · Not reviewed

Not addressed in bid

Page not available

Testing limited to domestic water lines; compressed air test at 1100 kPa not affirmed.

Capital Mechanical Inc. · Revision 1 · Pressure test compressed air system at 1100 kPa for 4 hours.

Compressed Air & Specialty Piping · page 1, item 21 · Excluded · Not reviewed

Section 22 15 00 — Compressed Air Systems: EXCLUDED. The Schedule 80 welded compressed air system as specified is outside our standard scope; we recommend this be carried by a specialty piping contractor or added as Alternate #2 below.

Bid_C_Capital_Mechanical.pdf, p. 2

Testing of the excluded compressed air system is not carried in base bid.

Reliable Mechanical Co. · Revision 1 · Bronze valves, CRN-registered, single manufacturer: gate, globe, check, ball and butterfly.

Compressed Air & Specialty Piping · page 1, item 22 · Included · Not reviewed

Section 23 05 23.01 — Bronze valves with CRN registration numbers from a single manufacturer, including gate, globe, check, ball, and butterfly valves at specified pressure ratings.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Bronze valves, CRN-registered, single manufacturer: gate, globe, check, ball and butterfly.

Compressed Air & Specialty Piping · page 1, item 22 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid names bronze gate, globe, check and ball valves; CRN registration, single manufacturer and butterfly valves not affirmed.

Capital Mechanical Inc. · Revision 1 · Bronze valves, CRN-registered, single manufacturer: gate, globe, check, ball and butterfly.

Compressed Air & Specialty Piping · page 1, item 22 · Included · Not reviewed

Section 23 05 23.01 — CRN-registered bronze valves from a single manufacturer including gate, globe, check, ball, and butterfly valves at the pressure classes specified.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · Pipe welding by CSA B51 qualified welders to ASME B31.1, procedures registered.

Compressed Air & Specialty Piping · page 1, item 23 · Included · Not reviewed

Section 23 05 17 — Pipe welding by CSA B51 qualified welders, ASME B31.1 procedures, welder identification symbols, registration of welding procedures, and all required inspections.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Pipe welding by CSA B51 qualified welders to ASME B31.1, procedures registered.

Compressed Air & Specialty Piping · page 1, item 23 · Silent · Not reviewed

Not addressed in bid

Page not available

No welding qualification language; bid's compressed air piping is threaded.

Capital Mechanical Inc. · Revision 1 · Pipe welding by CSA B51 qualified welders to ASME B31.1, procedures registered.

Compressed Air & Specialty Piping · page 1, item 23 · Included · Not reviewed

Section 23 05 17 — Pipe welding to ASME B31.1 with CSA B51 qualified welders, registered procedures, and welder identification symbols.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · Third-party weld inspection and radiography of welded joints.

Compressed Air & Specialty Piping · page 1, item 24 · Unclear · Not reviewed

Section 23 05 17 — Pipe welding by CSA B51 qualified welders, ASME B31.1 procedures, welder identification symbols, registration of welding procedures, and all required inspections.

Bid_A_Reliable_Mechanical.pdf, p. 1

"All required inspections" may not carry third-party inspection or radiography of welds.

Northern Plumbing Ltd. · Revision 1 · Third-party weld inspection and radiography of welded joints.

Compressed Air & Specialty Piping · page 1, item 24 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Third-party weld inspection and radiography of welded joints.

Compressed Air & Specialty Piping · page 1, item 24 · Silent · Not reviewed

Not addressed in bid

Page not available

Welding inclusion does not name third-party inspection or radiography.

Reliable Mechanical Co. · Revision 1 · Wet pipe sprinkler system designed and installed to NFPA 13, hydraulically calculated.

Fire Protection · page 1, item 25 · Included · Not reviewed

Section 21 13 13 — Wet Pipe Sprinkler Systems, designed and installed to NFPA 13, including hydraulic calculations using Hazen-Williams formula, ULC-listed devices, Manitoba-stamped professional engineer shop drawings, sprinkler heads, alarm valves, pipe hangers, mechanical couplings, and inspector's test connection.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Wet pipe sprinkler system designed and installed to NFPA 13, hydraulically calculated.

Fire Protection · page 1, item 25 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid engages Div 22 scope exhaustively but never addresses sprinklers; catch-all exclusion does not settle it.

Capital Mechanical Inc. · Revision 1 · Wet pipe sprinkler system designed and installed to NFPA 13, hydraulically calculated.

Fire Protection · page 1, item 25 · Excluded · Not reviewed

Section 21 13 13 — Wet Pipe Sprinkler Systems: EXCLUDED in entirety. We assume this scope is being bid by a dedicated fire protection / sprinkler contractor under Division 21. We will coordinate with that trade as required.

Bid_C_Capital_Mechanical.pdf, p. 2

Available as Alternate #1 for $86,500 add.

Reliable Mechanical Co. · Revision 1 · Manitoba-stamped PE shop drawings for sprinkler layout.

Fire Protection · page 1, item 26 · Included · Not reviewed

Section 21 13 13 — Wet Pipe Sprinkler Systems, designed and installed to NFPA 13, including hydraulic calculations using Hazen-Williams formula, ULC-listed devices, Manitoba-stamped professional engineer shop drawings, sprinkler heads, alarm valves, pipe hangers, mechanical couplings, and inspector's test connection.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Manitoba-stamped PE shop drawings for sprinkler layout.

Fire Protection · page 1, item 26 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Manitoba-stamped PE shop drawings for sprinkler layout.

Fire Protection · page 1, item 26 · Excluded · Not reviewed

Section 21 13 13 — Wet Pipe Sprinkler Systems: EXCLUDED in entirety. We assume this scope is being bid by a dedicated fire protection / sprinkler contractor under Division 21. We will coordinate with that trade as required.

Bid_C_Capital_Mechanical.pdf, p. 2

Sprinkler layout drawings fall within the excluded 21 13 13 scope.

Reliable Mechanical Co. · Revision 1 · Spare sprinkler heads and wrench cabinet per NFPA 13 minimum.

Fire Protection · page 1, item 27 · Silent · Not reviewed

Not addressed in bid

Page not available

Base bid names sprinkler heads but not spares or wrench cabinet; an add alternate prices spares "beyond NFPA 13 minimum", implying base may carry the minimum.

Northern Plumbing Ltd. · Revision 1 · Spare sprinkler heads and wrench cabinet per NFPA 13 minimum.

Fire Protection · page 1, item 27 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Spare sprinkler heads and wrench cabinet per NFPA 13 minimum.

Fire Protection · page 1, item 27 · Excluded · Not reviewed

Section 21 13 13 — Wet Pipe Sprinkler Systems: EXCLUDED in entirety. We assume this scope is being bid by a dedicated fire protection / sprinkler contractor under Division 21. We will coordinate with that trade as required.

Bid_C_Capital_Mechanical.pdf, p. 2

Spare heads and cabinet fall within the excluded sprinkler section.

Reliable Mechanical Co. · Revision 1 · Integrated systems testing of fire protection per CAN/ULC-S1001.

Fire Protection · page 1, item 28 · Included · Not reviewed

Integrated systems testing of fire protection per CAN/ULC-S1001.

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Integrated systems testing of fire protection per CAN/ULC-S1001.

Fire Protection · page 1, item 28 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Integrated systems testing of fire protection per CAN/ULC-S1001.

Fire Protection · page 1, item 28 · Excluded · Not reviewed

Excludes integrated systems testing under CAN/ULC-S1001 — typically administered by Fire Protection.

Bid_C_Capital_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Site painting of sprinkler piping: primer, finish coats, 50mm red enamel bands at 6m o.c.

Fire Protection · page 1, item 29 · Included · Not reviewed

Site painting of new sprinkler piping including pretreatment primer, primer, finish coats, and 50mm red enamel identification bands at 6m intervals per Section 21 13 13.

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Site painting of sprinkler piping: primer, finish coats, 50mm red enamel bands at 6m o.c.

Fire Protection · page 1, item 29 · Excluded · Not reviewed

Painting of any kind.

Bid_B_Northern_Plumbing.pdf, p. 1

Capital Mechanical Inc. · Revision 1 · Site painting of sprinkler piping: primer, finish coats, 50mm red enamel bands at 6m o.c.

Fire Protection · page 1, item 29 · Excluded · Not reviewed

Site painting of plumbing piping beyond shop primer (e.g., red enamel identification bands, finish coats in finished areas) — by Painting trade.

Bid_C_Capital_Mechanical.pdf, p. 2

Also within excluded sprinkler scope; confirm painting trade carries red enamel bands.

Reliable Mechanical Co. · Revision 1 · Pipe hangers and supports per MSS SP-58 with spacing per the spec table.

Hangers, Supports & Identification · page 1, item 30 · Included · Not reviewed

Section 23 05 29 — Pipe hangers and supports per MSS SP-58 with hanger spacing per the spec table; PE-stamped shop drawings for anchors, guides, and restraints; galvanized hangers for exterior locations; insulation protection shields.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Pipe hangers and supports per MSS SP-58 with spacing per the spec table.

Hangers, Supports & Identification · page 1, item 30 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid says hangers "per code"; MSS SP-58 and spec spacing table not affirmed.

Capital Mechanical Inc. · Revision 1 · Pipe hangers and supports per MSS SP-58 with spacing per the spec table.

Hangers, Supports & Identification · page 1, item 30 · Included · Not reviewed

Section 23 05 29 — Hangers and supports designed and installed per MSS SP-58 with spacing per the spec table; PE-stamped shop drawings for anchors and guides; insulation protection shields on hot piping.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · PE-stamped shop drawings for anchors, guides and seismic restraints.

Hangers, Supports & Identification · page 1, item 31 · Included · Not reviewed

Section 23 05 29 — Pipe hangers and supports per MSS SP-58 with hanger spacing per the spec table; PE-stamped shop drawings for anchors, guides, and restraints; galvanized hangers for exterior locations; insulation protection shields.

Bid_A_Reliable_Mechanical.pdf, p. 1

Bid says anchors, guides and restraints; "seismic" restraints not named explicitly.

Northern Plumbing Ltd. · Revision 1 · PE-stamped shop drawings for anchors, guides and seismic restraints.

Hangers, Supports & Identification · page 1, item 31 · Unclear · Not reviewed

Pipe hangers and supports per code.

Bid_B_Northern_Plumbing.pdf, p. 1

"Per code" may not carry seismic restraint engineering or PE-stamped shop drawings.

Capital Mechanical Inc. · Revision 1 · PE-stamped shop drawings for anchors, guides and seismic restraints.

Hangers, Supports & Identification · page 1, item 31 · Included · Not reviewed

Section 23 05 29 — Hangers and supports designed and installed per MSS SP-58 with spacing per the spec table; PE-stamped shop drawings for anchors and guides; insulation protection shields on hot piping.

Bid_C_Capital_Mechanical.pdf, p. 1

Bid names anchors and guides; seismic restraints not affirmed.

Reliable Mechanical Co. · Revision 1 · Galvanized hangers at exterior and unheated locations; insulation protection shields.

Hangers, Supports & Identification · page 1, item 32 · Included · Not reviewed

Section 23 05 29 — Pipe hangers and supports per MSS SP-58 with hanger spacing per the spec table; PE-stamped shop drawings for anchors, guides, and restraints; galvanized hangers for exterior locations; insulation protection shields.

Bid_A_Reliable_Mechanical.pdf, p. 1

Bid names exterior locations; unheated interior locations not specifically affirmed.

Northern Plumbing Ltd. · Revision 1 · Galvanized hangers at exterior and unheated locations; insulation protection shields.

Hangers, Supports & Identification · page 1, item 32 · Silent · Not reviewed

Not addressed in bid

Page not available

Galvanized hangers and insulation protection shields not named.

Capital Mechanical Inc. · Revision 1 · Galvanized hangers at exterior and unheated locations; insulation protection shields.

Hangers, Supports & Identification · page 1, item 32 · Included · Not reviewed

Section 23 05 29 — Hangers and supports designed and installed per MSS SP-58 with spacing per the spec table; PE-stamped shop drawings for anchors and guides; insulation protection shields on hot piping.

Bid_C_Capital_Mechanical.pdf, p. 1

Insulation protection shields affirmed; galvanized hangers at exterior/unheated locations not named.

Reliable Mechanical Co. · Revision 1 · Structural steel supports for equipment referenced to Section 05 12 23.

Hangers, Supports & Identification · page 1, item 33 · Excluded · Not reviewed

Excludes structural steel for equipment supports referenced to Section 05 12 23.

Bid_A_Reliable_Mechanical.pdf, p. 2

Scope sheet assigns this line to the package; confirm who carries the steel.

Northern Plumbing Ltd. · Revision 1 · Structural steel supports for equipment referenced to Section 05 12 23.

Hangers, Supports & Identification · page 1, item 33 · Silent · Not reviewed

Not addressed in bid

Page not available

Cross-section reference to 05 12 23; ownership of equipment steel supports unresolved.

Capital Mechanical Inc. · Revision 1 · Structural steel supports for equipment referenced to Section 05 12 23.

Hangers, Supports & Identification · page 1, item 33 · Excluded · Not reviewed

Excludes housekeeping pads (Section 03 30 00) and structural supports referenced to Section 05 12 23.

Bid_C_Capital_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Mechanical identification per CAN/CGSB-24.3: pipe legends, flow arrows, valve tags.

Hangers, Supports & Identification · page 1, item 34 · Included · Not reviewed

Section 23 05 53 — Mechanical identification per CAN/CGSB-24.3, including system nameplates, pipe identification with background colour, legends and flow arrows, valve tags with brass plates and 12mm stamped lettering, and flow diagrams for each system.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Mechanical identification per CAN/CGSB-24.3: pipe legends, flow arrows, valve tags.

Hangers, Supports & Identification · page 1, item 34 · Silent · Not reviewed

Not addressed in bid

Page not available

No pipe labelling, flow arrows or valve tags in the bid.

Capital Mechanical Inc. · Revision 1 · Mechanical identification per CAN/CGSB-24.3: pipe legends, flow arrows, valve tags.

Hangers, Supports & Identification · page 1, item 34 · Included · Not reviewed

Section 23 05 53 — Mechanical identification per CAN/CGSB-24.3 including pipe legends, background colour bands, flow arrows, valve tags with brass plates, and system flow diagrams.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · Thermometers and pressure gauges at equipment connections.

Hangers, Supports & Identification · page 1, item 35 · Excluded · Not reviewed

Excludes Section 23 05 19.13 (Thermometers and Pressure Gauges) — by HVAC trade.

Bid_A_Reliable_Mechanical.pdf, p. 2

Scope sheet assigns to this package; bid pushes to HVAC trade — confirm split.

Northern Plumbing Ltd. · Revision 1 · Thermometers and pressure gauges at equipment connections.

Hangers, Supports & Identification · page 1, item 35 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Thermometers and pressure gauges at equipment connections.

Hangers, Supports & Identification · page 1, item 35 · Excluded · Not reviewed

Excludes Section 23 05 19.13 thermometers and pressure gauges — by HVAC trade.

Bid_C_Capital_Mechanical.pdf, p. 2

Scope sheet assigns to this package; confirm HVAC trade carries gauges at plumbing equipment.

Reliable Mechanical Co. · Revision 1 · O&M manuals: equipment data, valve schedules, test certificates, subcontractor manuals.

Closeout · page 1, item 36 · Included · Not reviewed

Section 20 08 03.00 — Operating and maintenance manuals including equipment data, system data, valve schedules, subcontractor manuals for piping, air balancing, and sprinkler. As-built shop drawings, as-built construction drawings, originals of test forms and test certificates.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · O&M manuals: equipment data, valve schedules, test certificates, subcontractor manuals.

Closeout · page 1, item 36 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · O&M manuals: equipment data, valve schedules, test certificates, subcontractor manuals.

Closeout · page 1, item 36 · Included · Not reviewed

Section 20 08 03.00 — Equipment and system O&M; manuals, valve schedules, equipment name tags, filter schedules, subcontractor manuals for piping and air balancing, and as-built documentation including reviewed shop drawings, originals of test forms and test certificates.

Bid_C_Capital_Mechanical.pdf, p. 1

Reliable Mechanical Co. · Revision 1 · As-built drawings: reviewed shop drawings and marked-up construction set.

Closeout · page 1, item 37 · Included · Not reviewed

Section 20 08 03.00 — Operating and maintenance manuals including equipment data, system data, valve schedules, subcontractor manuals for piping, air balancing, and sprinkler. As-built shop drawings, as-built construction drawings, originals of test forms and test certificates.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · As-built drawings: reviewed shop drawings and marked-up construction set.

Closeout · page 1, item 37 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · As-built drawings: reviewed shop drawings and marked-up construction set.

Closeout · page 1, item 37 · Included · Not reviewed

Section 20 08 03.00 — Equipment and system O&M; manuals, valve schedules, equipment name tags, filter schedules, subcontractor manuals for piping and air balancing, and as-built documentation including reviewed shop drawings, originals of test forms and test certificates.

Bid_C_Capital_Mechanical.pdf, p. 1

As-built documentation and reviewed shop drawings named; marked-up construction set not explicitly affirmed.

Reliable Mechanical Co. · Revision 1 · Owner training: five (5) Working Days of instruction for the Owner's representative.

Closeout · page 2, item 38 · Included · Not reviewed

Owner training: Five (5) Working Days of instruction for the Owner's representative per Section 20 08 03.00, including arrangements and fees for manufacturer representatives.

Bid_A_Reliable_Mechanical.pdf, p. 1

Northern Plumbing Ltd. · Revision 1 · Owner training: five (5) Working Days of instruction for the Owner's representative.

Closeout · page 2, item 38 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Owner training: five (5) Working Days of instruction for the Owner's representative.

Closeout · page 2, item 38 · Excluded · Not reviewed

Owner training in excess of 1 day: Section 20 08 03.00 specifies five (5) Working Days of training. Our base bid includes only one (1) day; additional days available as Alternate #4.

Bid_C_Capital_Mechanical.pdf, p. 2

Base bid carries only 1 of 5 required days; remaining 4 days are Alternate #4 at $7,800.

Reliable Mechanical Co. · Revision 1 · One-year warranty on all labour and materials from Substantial Performance.

Closeout · page 2, item 39 · Silent · Not reviewed

Not addressed in bid

Page not available

No warranty term stated anywhere in the bid; confirm one-year labour and materials warranty.

Northern Plumbing Ltd. · Revision 1 · One-year warranty on all labour and materials from Substantial Performance.

Closeout · page 2, item 39 · Unclear · Not reviewed

Standard manufacturer's warranty on all installed plumbing systems.

Bid_B_Northern_Plumbing.pdf, p. 1

Manufacturer's warranty may not equal one-year labour and materials from Substantial Performance.

Capital Mechanical Inc. · Revision 1 · One-year warranty on all labour and materials from Substantial Performance.

Closeout · page 2, item 39 · Included · Not reviewed

One-year manufacturer's warranty on installed plumbing systems and equipment.

Bid_C_Capital_Mechanical.pdf, p. 2

Bid offers manufacturer's warranty; labour warranty from Substantial Performance not explicitly affirmed.

Reliable Mechanical Co. · Revision 1 · Final cleaning and removal of all debris from work areas.

Closeout · page 2, item 40 · Silent · Not reviewed

Not addressed in bid

Page not available

Bid does not address final cleaning or debris removal.

Northern Plumbing Ltd. · Revision 1 · Final cleaning and removal of all debris from work areas.

Closeout · page 2, item 40 · Silent · Not reviewed

Not addressed in bid

Page not available

Capital Mechanical Inc. · Revision 1 · Final cleaning and removal of all debris from work areas.

Closeout · page 2, item 40 · Silent · Not reviewed

Not addressed in bid

Page not available

No mention of final cleaning or debris removal.

Reliable Mechanical Co. · Revision 1 · Qualification

Bid details · · ·

Bid Bond included with this submission.

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Qualification

Bid details · · ·

Pricing valid for 60 days from bid date.

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Qualification

Bid details · · ·

Material escalation clause: pricing subject to review if project NTP delayed beyond 90 days from bid date.

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Qualification

Bid details · · ·

Twelve (12) weeks from Notice to Proceed for plumbing rough-in and finish, subject to overall project schedule and confirmed material lead times. Sprinkler system completion within overall mechanical milestone.

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Alternate

Bid details · · ·

Add Performance and Payment Bonds · CAD 8500

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Alternate

Bid details · · ·

Stainless steel valves in lieu of bronze in lab compressed air loop · CAD 14200

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Alternate

Bid details · · ·

Provide one additional spare set of sprinkler heads beyond NFPA 13 minimum · CAD 1800

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Schedule

Bid details · · ·

12 weeks

Bid_A_Reliable_Mechanical.pdf, p. 2

Reliable Mechanical Co. · Revision 1 · Price validity

Bid details · · ·

60 days

Bid_A_Reliable_Mechanical.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Qualification

Bid details · · ·

Pricing valid for 30 days.

Bid_B_Northern_Plumbing.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Qualification

Bid details · · ·

Standard work hours Monday to Friday 7:00 AM to 4:00 PM. After-hours billed extra.

Bid_B_Northern_Plumbing.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Qualification

Bid details · · ·

Net 30 payment terms.

Bid_B_Northern_Plumbing.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Qualification

Bid details · · ·

Subject to acceptable credit review.

Bid_B_Northern_Plumbing.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Schedule

Bid details · · ·

14 weeks

Bid_B_Northern_Plumbing.pdf, p. 2

Northern Plumbing Ltd. · Revision 1 · Price validity

Bid details · · ·

30 days

Bid_B_Northern_Plumbing.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Qualification

Bid details · · ·

Pricing valid for 45 days from bid date.

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Qualification

Bid details · · ·

Material escalation clause for steel and copper applies if NTP delayed beyond 60 days.

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Qualification

Bid details · · ·

Net 30 payment terms with monthly progress draws.

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Qualification

Bid details · · ·

Plumbing rough-in and finish: ten (10) weeks from Notice to Proceed, subject to confirmed material lead times and overall mechanical schedule. Compressed air system (if Alt #2 awarded) adds two (2) weeks.

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Alternate

Bid details · · ·

ADD Sprinkler scope (Section 21 13 13) using our approved sub-tier fire protection contractor · CAD 86500

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Alternate

Bid details · · ·

ADD Section 22 15 00 Compressed Air Systems (Schedule 80 welded) · CAD 34200

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Alternate

Bid details · · ·

ADD Performance and Payment Bonds: ADD 2.0% of contract value · Not priced

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Alternate

Bid details · · ·

ADD remaining 4 days of Owner training to satisfy Section 20 08 03.00 five-day requirement · CAD 7800

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Schedule

Bid details · · ·

10 weeks

Bid_C_Capital_Mechanical.pdf, p. 2

Capital Mechanical Inc. · Revision 1 · Price validity

Bid details · · ·

45 days

Bid_C_Capital_Mechanical.pdf, p. 2

Adjustments

None entered

About

ItemDetails
ProjectSample project
Bid packagePlumbing — Div 22
Scope lines fromTemplate: plumbing-scope-sheet.pdf (PDF)
Synthetic sampleSynthetic scope and bids. Recorded Prestead analysis. This demonstrates the workflow, not measured accuracy. Analysis recorded 2026-09-06T06:52:19.095Z.
Bids3 of 3 uploaded analyzed
ExportedExported by Sample estimator on Sep 5, 2026
Pipeline versionstemplate-parsing 2026-09-05.1; bid-parsing 2026-09-05.1; gap-analysis 2026-09-05.1; clarification-drafting 2026-09-05.1
Analysis boundaryPrestead fills your scope template from the uploaded bid PDFs only. The spec and drawings are not reviewed.
Analysis boundaryCarries and adjustments are estimator-entered — not AI estimates.
Analysis boundaryAlternate amounts are the bid's own figures, cited to a page.
Omitted submissionsNone
AuthorshipPrestead read the uploaded bids against the scope lines and marked each line included, excluded, unclear, or silent. Costs and corrections are human-entered, with their original authorship recorded. Review labels identify assessments explicitly checked by a user. Unreviewed and incomplete results remain qualified.

In the print dialog, choose Save as PDF.